In Project 2000, how can I change the duration into seconds?

K

kvaught

I would like to set up a chemical batch cycle, which requires changing the
duration into seconds. Is this possible?
 
J

John

kvaught said:
I would like to set up a chemical batch cycle, which requires changing the
duration into seconds. Is this possible?

Kvaught,
This type of question has been asked multiple times in the newsgroup.
Project works in minutes and wasn't really designed to plan specialized
process type activities such as you have. You could pretend that a
second is really a minute but then things fall apart when the dimension
gets to hours because there are of course only 8 hours in a day, not 60.

John
 
J

JackD

You can set it to 24 hours which would translate into 24 minutes.
With a calculated field I think you could possibly do this...

Interesting problem.
 