kvaught said:
I would like to set up a chemical batch cycle, which requires changing the
duration into seconds. Is this possible?
Kvaught,
This type of question has been asked multiple times in the newsgroup.
Project works in minutes and wasn't really designed to plan specialized
process type activities such as you have. You could pretend that a
second is really a minute but then things fall apart when the dimension
gets to hours because there are of course only 8 hours in a day, not 60.
John