G
Gene
We are using Project Server 2003 and have a number of Enterprise Task
Text fields that display some indicator to show if the task is on-time,
etc. The problem is when using Project Pro 2003 we have not found a
calculation that recognizes if a task has been baselined. The
Enterprise Task Text filed displays #ERROR if the calculated field
tries to use a non-baselined field in a calculation. Can someone give
me a formula to identified that a baseline field has not been populated
(i.e. Baseline Start has not been populated)?
Text fields that display some indicator to show if the task is on-time,
etc. The problem is when using Project Pro 2003 we have not found a
calculation that recognizes if a task has been baselined. The
Enterprise Task Text filed displays #ERROR if the calculated field
tries to use a non-baselined field in a calculation. Can someone give
me a formula to identified that a baseline field has not been populated
(i.e. Baseline Start has not been populated)?