J
Jennifer L
Upon opening certain projects in MS Project Professional 2007 I continue to
receive the warning message that my… “inactive resources still have remaining
work and that I should reassign that work to an active resource.†However, I
have made sure that those tasks assigned to the inactive resources are marked
100% complete. They are done – there is no remaining work to be reassigned. I
have even gone back into the Resource Center in Project Server, switched
these resources from ‘inactive’ to ‘active’, then opened the project in MS
Project Pro 2007 (when the resource is set to active I do not get the warning
message), made sure the tasks were updated, saved and published the project,
checked-in the project, cleared my cache and exited the application. I then
made the resources ‘inactive’ again (as they should be), opened the app and
the project, but still got the warning message about my inactive resources.
Is there a way to make these warning messages go away? This gets especially
annoying when opening the Master project, as there are inactive resources on
multiple projects. Have I not done all there is to do to ensure that the work
is showing as complete on these assignments? Please let me know if there’s
something I’m missing. Any help is appreciated.
Thank you!
Jennifer
receive the warning message that my… “inactive resources still have remaining
work and that I should reassign that work to an active resource.†However, I
have made sure that those tasks assigned to the inactive resources are marked
100% complete. They are done – there is no remaining work to be reassigned. I
have even gone back into the Resource Center in Project Server, switched
these resources from ‘inactive’ to ‘active’, then opened the project in MS
Project Pro 2007 (when the resource is set to active I do not get the warning
message), made sure the tasks were updated, saved and published the project,
checked-in the project, cleared my cache and exited the application. I then
made the resources ‘inactive’ again (as they should be), opened the app and
the project, but still got the warning message about my inactive resources.
Is there a way to make these warning messages go away? This gets especially
annoying when opening the Master project, as there are inactive resources on
multiple projects. Have I not done all there is to do to ensure that the work
is showing as complete on these assignments? Please let me know if there’s
something I’m missing. Any help is appreciated.
Thank you!
Jennifer