A
Alice Roberts
Hi all,
I have an activity plan I am maintaining in PWA
It has some completed tasks that have resources assigned who are now
inactive (have left the organisation).
When I go to add new tasks to this plan and I assign them to a new
active resource. I get the error
" You cannot assign a task to an inactive resource or a resource that
cannot have assignments.... "
The point is that I am not changing the old, historical and completed
tasks. I merely want to add a new task which has an active and current
user/resource.
Is this possible at all, it seems to me the only option is to delete
the task or remove the old assignment.
Thanks for any help.
regards
Alice
I have an activity plan I am maintaining in PWA
It has some completed tasks that have resources assigned who are now
inactive (have left the organisation).
When I go to add new tasks to this plan and I assign them to a new
active resource. I get the error
" You cannot assign a task to an inactive resource or a resource that
cannot have assignments.... "
The point is that I am not changing the old, historical and completed
tasks. I merely want to add a new task which has an active and current
user/resource.
Is this possible at all, it seems to me the only option is to delete
the task or remove the old assignment.
Thanks for any help.
regards
Alice