After an employee leaves and we have set their status to 'inactive', project
plans that they had been assigned to (for example, admin: vacation, sick
time, etc) pops up with a warning saying:
Inactive resources will be unable to report status so their remaining work
should be assigned to active resources.
So my question is: how do I do this regarding an admin project? Will the
system allow me to simply delete the resource from the task? I would think
this would not work since there are actuals tied to the task.
There are multiple people assigned to admin tasks - so there is no
'remaining work' to reassign. Any insight?
Thanks!
NYC
After an employee leaves and we have set their status to 'inactive', project
plans that they had been assigned to (for example, admin: vacation, sick
time, etc) pops up with a warning saying:
Inactive resources will be unable to report status so their remaining work
should be assigned to active resources.
So my question is: how do I do this regarding an admin project? Will the
system allow me to simply delete the resource from the task? I would think
this would not work since there are actuals tied to the task.
There are multiple people assigned to admin tasks - so there is no
'remaining work' to reassign. Any insight?