Inavlid Node name Parameter specified .... what does this mean????

J

Jim Crawford

I have two resources that were marked inactive... I now need to mark them
active again. I open the enterprise resource pool, and select the two
resources. For each of them I uncheck the inactive box and then I try to save
them back to the enterprise resource pool. I get the following message:
Project server was unable to process the request. An invalid node name
parameter was specified....
From a users perspective this is a truly meaningless error message. Any
possible enlightenment would be appreciated.
 
J

Jim Crawford

Thanks! That did it!

Reid McTaggart said:
Try changing their status from PWA.
--
Reid McTaggart
Alegient, Inc., Houston
Project Server Experts
Microsoft Certified Partner
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top