F
Frank
hey - we are using PWA for time reporting - thus i
included task id numbers to the individual tasks - so the
resource can also see the actual job number he is booking
on - i did this by entering a text colum at project
desktop and defined it so it appears as task id coloum
before the task name in PWA.
So far so good - only that it totally messed up the order
in which the tasks appear on PWA task view! Now some tasks
(for users with more then one project assigned to) are
listed underneath different projects and not underneath
the ones they are part of! if i remove the task id colum
the go back to their right order! what can i do to be able
to use the "text colum" function without messing with the
PWA task view strukture?
Also if i enter the "text colum" it appears for all
projects - but one of the projet is admin only thus has no
task id - there the colum still appears though - any
possibility to correct that???
thanks
Frank
included task id numbers to the individual tasks - so the
resource can also see the actual job number he is booking
on - i did this by entering a text colum at project
desktop and defined it so it appears as task id coloum
before the task name in PWA.
So far so good - only that it totally messed up the order
in which the tasks appear on PWA task view! Now some tasks
(for users with more then one project assigned to) are
listed underneath different projects and not underneath
the ones they are part of! if i remove the task id colum
the go back to their right order! what can i do to be able
to use the "text colum" function without messing with the
PWA task view strukture?
Also if i enter the "text colum" it appears for all
projects - but one of the projet is admin only thus has no
task id - there the colum still appears though - any
possibility to correct that???
thanks
Frank