I have MS Project 2003. If I enter a duration of 5 days I would expect the
(eg) start date to be Monday 19th & to finish on Friday 23rd but it shows a
finish date of Monday 26th. If I enter 4 days it shows a finish date of
23rd. Is there a setting to change this? Or I am just cinfused!