Daniel Zitter - Matan Consulting
I encountered a problem of inconsistency between the project professional and
the "Tasks" tab in PWA.
A resource reported on a task twice:
In the first time, the report was: "% work completed = 100 %", the report
was updated in the project plan and in PWA successfully.
After a week, a second report for the same task was: "% work completed = 95
%" (% work completed decreased)
I accepted the report, saved the project plan file and published it again.
The Project Professional file and the project in the project center was
updated correctly, in the "tasks" tab the resource still sees "% work
completed = 100%" (in the project center the task is updated correctly to
95%).
The report method is "Percent of work complete" and we are using MSP 2003.
What could cause this problem?
=======================
Daniel Zitter
the "Tasks" tab in PWA.
A resource reported on a task twice:
In the first time, the report was: "% work completed = 100 %", the report
was updated in the project plan and in PWA successfully.
After a week, a second report for the same task was: "% work completed = 95
%" (% work completed decreased)
I accepted the report, saved the project plan file and published it again.
The Project Professional file and the project in the project center was
updated correctly, in the "tasks" tab the resource still sees "% work
completed = 100%" (in the project center the task is updated correctly to
95%).
The report method is "Percent of work complete" and we are using MSP 2003.
What could cause this problem?
=======================
Daniel Zitter