inconsistency between MSP & "Tasks" in PWA

  • Thread starter Daniel Zitter - Matan Consulting
  • Start date
D

Daniel Zitter - Matan Consulting

I encountered a problem of inconsistency between the project professional and
the "Tasks" tab in PWA.

A resource reported on a task twice:
In the first time, the report was: "% work completed = 100 %", the report
was updated in the project plan and in PWA successfully.
After a week, a second report for the same task was: "% work completed = 95
%" (% work completed decreased)
I accepted the report, saved the project plan file and published it again.
The Project Professional file and the project in the project center was
updated correctly, in the "tasks" tab the resource still sees "% work
completed = 100%" (in the project center the task is updated correctly to
95%).

The report method is "Percent of work complete" and we are using MSP 2003.
What could cause this problem?

=======================
Daniel Zitter
 
M

Mike Glen

Hi Daniel,

Try posting on the server newsgroup. Please see FAQ Item: 24. Project
Newsgroups. FAQs, companion products and other useful Project information
can be seen at this web address: http://www.mvps.org/project/.

Mike Glen
Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top