Theo
Environment: EPM SP2, Project 2007 SP1
For a long time we have problems in the processing of hours.
For excample:
In the timesheet a user enters a total amount of 40 hours. After the
taskupdate they are not seen in the MSP_POortfolio Anlyzer. However
when opening the project in MS-Project the 40 hours are de processed
as acutal hours.
Because I do a lot of reporting via de cubus I never have the right
actuals calculated.
The total difference for 2009 is about 10%.
Has one of you an idea what the problem could be and how to solve this.
For a long time we have problems in the processing of hours.
For excample:
In the timesheet a user enters a total amount of 40 hours. After the
taskupdate they are not seen in the MSP_POortfolio Anlyzer. However
when opening the project in MS-Project the 40 hours are de processed
as acutal hours.
Because I do a lot of reporting via de cubus I never have the right
actuals calculated.
The total difference for 2009 is about 10%.
Has one of you an idea what the problem could be and how to solve this.