C
Charles
Work days specified as 7 days per week. 0800-1200, 1300-1700, Sunday thru
Saturday. If I put a duration of 60 days in it goes out much further, so it
must only be using Mon-Fri work week. Why isn't it using the work week
defined in Tools-Change Working Time? I made every day a work week, but when
I put duration in it does not count Sat and Sun as part of the duration.
Thus the finish date is further out than desired. Why? Thanks.
Saturday. If I put a duration of 60 days in it goes out much further, so it
must only be using Mon-Fri work week. Why isn't it using the work week
defined in Tools-Change Working Time? I made every day a work week, but when
I put duration in it does not count Sat and Sun as part of the duration.
Thus the finish date is further out than desired. Why? Thanks.