I am seeing what appears to be an incorrect assignment of remaining work.
I have a single resource assigned to a particular task that is currently 99%
complete. There is .32 days remaining work to complete. The resource is not
allocated to any other tasks. At this point, I would expect the task to be
done in 1 day (.32 day).
However, after leveling, the resouce usage view reports 4 days @ 1.14 days
(overallocating by .14 per day), and .86 days work required to complete the
task.
Why isn't this task permitted to complete in 1 (or .32) days? Why does
project overallocate the resource for the 4 days and apparently needlessly
stretch the duration an extra 5 days? Please help.
I have a single resource assigned to a particular task that is currently 99%
complete. There is .32 days remaining work to complete. The resource is not
allocated to any other tasks. At this point, I would expect the task to be
done in 1 day (.32 day).
However, after leveling, the resouce usage view reports 4 days @ 1.14 days
(overallocating by .14 per day), and .86 days work required to complete the
task.
Why isn't this task permitted to complete in 1 (or .32) days? Why does
project overallocate the resource for the 4 days and apparently needlessly
stretch the duration an extra 5 days? Please help.