I was stuck whole day for the incorrect BCWP & SPI.
One of my colleagus sent me an exmple of plan, trying the EV. I found
the baseline has saved, most of the tasks have correct EV datas except
one, I named it as task A. Whose finish date is extended compared to
the baseline. When I put the project status date in the future -- after
the finish of project. I found when I change the % complete of task A,
the BCWP & SPI do not changed accordingly. I copied the data I recorded
below. Who could tell me the reason.
SPI % BCWP AC
0.2 0.1 6.3 7.8
0.39 0.2 12.6 15.6
0.46 0.3 14.87 23.4
0.47 0.4 14.9 31.2
0.47 0.5 14.93 39
0.47 0.6 14.96 46.8
0.47 0.7 14.99 54.6
0.61 0.8 19.4 62.4
0.8 0.9 25.7 70.2
1 1 32 78
One of my colleagus sent me an exmple of plan, trying the EV. I found
the baseline has saved, most of the tasks have correct EV datas except
one, I named it as task A. Whose finish date is extended compared to
the baseline. When I put the project status date in the future -- after
the finish of project. I found when I change the % complete of task A,
the BCWP & SPI do not changed accordingly. I copied the data I recorded
below. Who could tell me the reason.
SPI % BCWP AC
0.2 0.1 6.3 7.8
0.39 0.2 12.6 15.6
0.46 0.3 14.87 23.4
0.47 0.4 14.9 31.2
0.47 0.5 14.93 39
0.47 0.6 14.96 46.8
0.47 0.7 14.99 54.6
0.61 0.8 19.4 62.4
0.8 0.9 25.7 70.2
1 1 32 78