Frank Moyer
We are using Project 2002 and we are having problems with the cost
calculated for a few tasks. An example is that a resources is assigned
to a task. The resource has only costs in cost rate A and only one
entry. The cost is $60.39/h. The task has 16 hours of Actual Work and
0 hours remaining, giving the work value of 16. So, I expect the cost
to be $966.24. However, it is showing up as $483.12. I have checked
that the costs are calculated automatically and everything looks
correct. Any ideas on what could be causing this?
Frank