Incorrect Costs

F

Frank Moyer

We are using Project 2002 and we are having problems with the cost
calculated for a few tasks. An example is that a resources is assigned
to a task. The resource has only costs in cost rate A and only one
entry. The cost is $60.39/h. The task has 16 hours of Actual Work and
0 hours remaining, giving the work value of 16. So, I expect the cost
to be $966.24. However, it is showing up as $483.12. I have checked
that the costs are calculated automatically and everything looks
correct. Any ideas on what could be causing this?

Frank
 
M

Mike Glen

Hi Frank,

No idea:-( Is it the Actual cost, Cost or Baseline cost that you're talking
about? Is it showing up as 100% Complete?

Please use the Project 2002 newsgroups referenced in FAQ No 24: Project and
Project VBA Newsgroups, at this web address: http://www.mvps.org/project/ .
You are more likely to get an answer there.


Mike Glen
MS Project MVP
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top