P
Puppa Romeo
I'm using the 2003 version of Project. I have a number of linked tasks by
finish to start, but some of the tasks are not showing the correct
start/finish dates. For example a task whose predecessor ends 08/09/09 should
begin 08/09/09 but is starting 15/10/09. The constraints are all set to "as
soon as possible". I've tried manually amending the date but with no success.
Any ideas?
finish to start, but some of the tasks are not showing the correct
start/finish dates. For example a task whose predecessor ends 08/09/09 should
begin 08/09/09 but is starting 15/10/09. The constraints are all set to "as
soon as possible". I've tried manually amending the date but with no success.
Any ideas?