Hello,
I think it's the normal behavior of a baselined data :
The summary was baselined at $10000 for instance with 3 children tasks. You
delete a children task which was baselined at $2000.
The summary baseline stays at $10000 but Project displays a Variance of -
2000 .
Anyway, you can baseline the project a second time and clear the variance.
Gérard Ducouret [Project MVP]