incorrect value in summary tasks for the baseline cost fields.

G

Gérard Ducouret

Hello,
I think it's the normal behavior of a baselined data :
The summary was baselined at $10000 for instance with 3 children tasks. You
delete a children task which was baselined at $2000.
The summary baseline stays at $10000 but Project displays a Variance of -
2000 .

Anyway, you can baseline the project a second time and clear the variance.

Gérard Ducouret [Project MVP]
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top