In Project 2007, I can correctly run the Budget Work Report Visual Report for
a project. However, I would like to run the Budget Work Report for multiple
projects (all of which are on our Project Server). To accomplish this, I am
inserting the second project into the first project, and running the Budget
Work Report. When completed, the Work hours are doubled for all projects.
For example, Project A is a 100 hour project. I run the Budget Work Report
and I see the report for 100 hours. I then insert Project B, another 100
hour project, into the Project A plan. The total work in the Project
Schedule (Gantt View) is correctly stated as 200 hours. I now run the Budget
Work Report, but the total number of Work hours is 400. Project A is 200
hours and Project B is 200 hours in the report.
Hcw can I properly run the Budget Work Report with multiple projects and get
accurate Work calcuations?
Thanks in advance.
a project. However, I would like to run the Budget Work Report for multiple
projects (all of which are on our Project Server). To accomplish this, I am
inserting the second project into the first project, and running the Budget
Work Report. When completed, the Work hours are doubled for all projects.
For example, Project A is a 100 hour project. I run the Budget Work Report
and I see the report for 100 hours. I then insert Project B, another 100
hour project, into the Project A plan. The total work in the Project
Schedule (Gantt View) is correctly stated as 200 hours. I now run the Budget
Work Report, but the total number of Work hours is 400. Project A is 200
hours and Project B is 200 hours in the report.
Hcw can I properly run the Budget Work Report with multiple projects and get
accurate Work calcuations?
Thanks in advance.