L
Long
Hi everyone,
My company is using Project Professional 2003 with Project Server and
Project Web Access. I am having a problem like this:
- There were old administrative projects storing working hours of employees
in 2005 until March 2006.
- New administrative projects were created based on those old project files,
with the aim of storing only working hours of 2006.
- The old admin. projects were put in archive after that, now only admin
(like me) can see the old projects.
The problem is:
- In the new admin projects, there are some strange hours. Some employees
say they did not enter it, but it shows they have. In some case, even 200,
300hours extra. In some cases, I see a task with 8h/a day for a long period
of time.
- And I check with Adjust actuals in Resources menu of PWA, I saw the old
admin projects were still showed (and probably the hours of those projects
are still counted). I set the Booking type of all people in old admin
projects to Proposed and put the projects in archive, how come it still show
these projects in the list of Adjust actuals ? (It does not show in Tasks
menu though)
How could I check and put the new admin. projects in correct hours ? If it
is going like this, it will be a big problem because in my company, there is
a lot of subsidised projects which really needs the correct hours.
Thank so much in advance
Long
My company is using Project Professional 2003 with Project Server and
Project Web Access. I am having a problem like this:
- There were old administrative projects storing working hours of employees
in 2005 until March 2006.
- New administrative projects were created based on those old project files,
with the aim of storing only working hours of 2006.
- The old admin. projects were put in archive after that, now only admin
(like me) can see the old projects.
The problem is:
- In the new admin projects, there are some strange hours. Some employees
say they did not enter it, but it shows they have. In some case, even 200,
300hours extra. In some cases, I see a task with 8h/a day for a long period
of time.
- And I check with Adjust actuals in Resources menu of PWA, I saw the old
admin projects were still showed (and probably the hours of those projects
are still counted). I set the Booking type of all people in old admin
projects to Proposed and put the projects in archive, how come it still show
these projects in the list of Adjust actuals ? (It does not show in Tasks
menu though)
How could I check and put the new admin. projects in correct hours ? If it
is going like this, it will be a big problem because in my company, there is
a lot of subsidised projects which really needs the correct hours.
Thank so much in advance
Long