I'm using MS Project 2003...
I have two consecutive dates where my planned work exceeds my allowed
percentage of 80%. I want to increase the allowed percentage for the
previous two days and these two days to 100%. I open the resource
information screen and increase the percentage to 100% for those four days,
however, when I save my changes it updates every day on that task to 100%.
What am I missing or doing wrong?