O
OTS
In this particular project i have 10 rows of tasks
then i decide to call the 1st task as the SUMMARY TASK; and rests are the
SUBTASK.
to do that, I will shade the row 2 to 10.
Then click INDENT
Then the row 2 until row 10 will become the SUBTASK task 1. The task name
now becomes BOLD.
Task 1 now the SUMMARY TASK, will take a bar shape. Task 2 until 9 will be
a subset of Task 1.
Let's say I change my mind -- and no longer need Task 1 as the SUMAMRY
TASK. And I like to put them on a similar hierachy.
What I need to do now is to shadow row 9 until row 10, and click OUTDENT.
But nothing happen at all.
Why?
Is that any setting that prevent the OUTDENT from functioning?
I expect to see all them become similar in the hierachy -- and all of them
as simply TASKS.
Thanks
then i decide to call the 1st task as the SUMMARY TASK; and rests are the
SUBTASK.
to do that, I will shade the row 2 to 10.
Then click INDENT
Then the row 2 until row 10 will become the SUBTASK task 1. The task name
now becomes BOLD.
Task 1 now the SUMMARY TASK, will take a bar shape. Task 2 until 9 will be
a subset of Task 1.
Let's say I change my mind -- and no longer need Task 1 as the SUMAMRY
TASK. And I like to put them on a similar hierachy.
What I need to do now is to shadow row 9 until row 10, and click OUTDENT.
But nothing happen at all.
Why?
Is that any setting that prevent the OUTDENT from functioning?
I expect to see all them become similar in the hierachy -- and all of them
as simply TASKS.