I am using MS Project 2007 Standard on Windows XP. I was working on a large
project file (>200 rows) when all of a sudden none of the child tasks are
indented in the task name field. If I click on a summary task, they
collapse. I checked tools/options/view "Indent name" and it was checked. I
tried unchecking and checking, but nothing changed. I closed the project
file and create a brand new file and any time I create a child task, it
doesn't indent. I rebootted, no change. I reinstalled MS Project, but no
change. I sent a file I created to a colleague, and the file shows child
tasks properly indented from parent tasks. Any ideas why this bizarre
behavior? Is there some global setting on my PC that is causing this?
 
K

Kerry

Based on another post below, I tried undocking my laptop and voila, the
indentation appears again. Redock, and it's gone. For some reason when I am
docked the indentation is either absent, or so slight, that it is
indiscernible. It is very difficult to work in project without indentation
being visible.
 