Steph said:
How do you get subtasks to be indented on reports as they
are in the Gantt Chart view? Every report I've tried shows
summary tasks and subtasks flush left.
TIA
You can't do that. You can export the data to excel and have the tasks
indented, but it helps if you know some vba. I have an example which does
this on my website that you can look at:
http://masamiki.com/project/macros.htm
Look for the export hierarchy to excel macro and use it as a starting point.
You can export just about any information you want using this method.
--
Please try to keep replies in this group. I do check e-mail, but only
infrequently. For Macros and other things check
http://masamiki.com/project
-Jack Dahlgren, Project MVP
+++++++++++++++++++