Indention Problems

Z

Zardon

When I indent, the preceeding task's duration changes to the same duration as
the current task. Also, when when unindenting or unoutdenting, how do you
remove or change the designation of summary or sub-task.
 
Z

Zardon

Yes, the info was helpful, thanks. When a subtask is mistakenly outindented
and made a summary, how do you unsummarize it. Deleting the contents doesn't
work and I don't want to affect the other subtasks or the original summary.
 
J

Jan De Messemaeker

Hi,

Are you by any chance working on Project 2003 Standard, without Srervice
Release? In that release there is a problem with outdenting<; <if so,n apply
the Service Packs.
If not, simply outdent.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
Zardon said:
Yes, the info was helpful, thanks. When a subtask is mistakenly
outindented
and made a summary, how do you unsummarize it. Deleting the contents
doesn't
work and I don't want to affect the other subtasks or the original
summary.

Mike Glen said:
Hi Zardon,

Welcome to this Microsoft Project newsgroup :)

When you indent tasks the one above automatically becomes a Summary. Its
Duration is governed by the tasks it's summarizing and is the working
time
between the start of the first task to the finish of the last task.

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine at this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen
at this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP



-----Original Message-----
From: Zardon [mailto:[email protected]]
Posted At: 13 March 2009 18:49
Posted To: microsoft.public.project
Conversation: Indention Problems
Subject: Indention Problems

When I indent, the preceeding task's duration changes to the same
duration
as
the current task. Also, when when unindenting or unoutdenting, how do you
remove or change the designation of summary or sub-task.
 
M

Mike Glen

You're welcome, Zardon :)

Select the tasks under the summary and then outdent.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials


Zardon said:
Yes, the info was helpful, thanks. When a subtask is mistakenly
outindented
and made a summary, how do you unsummarize it. Deleting the contents
doesn't
work and I don't want to affect the other subtasks or the original
summary.

Mike Glen said:
Hi Zardon,

Welcome to this Microsoft Project newsgroup :)

When you indent tasks the one above automatically becomes a Summary. Its
Duration is governed by the tasks it's summarizing and is the working
time
between the start of the first task to the finish of the last task.

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine at this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen
at this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP



-----Original Message-----
From: Zardon [mailto:[email protected]]
Posted At: 13 March 2009 18:49
Posted To: microsoft.public.project
Conversation: Indention Problems
Subject: Indention Problems

When I indent, the preceeding task's duration changes to the same
duration
as
the current task. Also, when when unindenting or unoutdenting, how do you
remove or change the designation of summary or sub-task.
 
Z

Zardon

I tried that. Initially, I indented using the space bar then move everything
back and used the indent icon. Could this have corrupted the indent function?
I opened a new file and tried part of it. It works ok.

Thanks,
Zardon

Mike Glen said:
You're welcome, Zardon :)

Select the tasks under the summary and then outdent.

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials


Zardon said:
Yes, the info was helpful, thanks. When a subtask is mistakenly
outindented
and made a summary, how do you unsummarize it. Deleting the contents
doesn't
work and I don't want to affect the other subtasks or the original
summary.

Mike Glen said:
Hi Zardon,

Welcome to this Microsoft Project newsgroup :)

When you indent tasks the one above automatically becomes a Summary. Its
Duration is governed by the tasks it's summarizing and is the working
time
between the start of the first task to the finish of the last task.

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine at this site: http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen
at this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP



-----Original Message-----
From: Zardon [mailto:[email protected]]
Posted At: 13 March 2009 18:49
Posted To: microsoft.public.project
Conversation: Indention Problems
Subject: Indention Problems

When I indent, the preceeding task's duration changes to the same
duration
as
the current task. Also, when when unindenting or unoutdenting, how do you
remove or change the designation of summary or sub-task.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top