Hi Zardon,
Welcome to this Microsoft Project newsgroup
When you indent tasks the one above automatically becomes a Summary. Its
Duration is governed by the tasks it's summarizing and is the working
time
between the start of the first task to the finish of the last task.
You might like to have a look at my series on Microsoft Project in the
TechTrax ezine at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site,

Thanks.)
FAQs, companion products and other useful Project information can be seen
at this web address: <
http://www.mvps.org/project/>
Hope this helps - please let us know how you get on
Mike Glen
MS Project MVP
-----Original Message-----
From: Zardon [mailto:
[email protected]]
Posted At: 13 March 2009 18:49
Posted To: microsoft.public.project
Conversation: Indention Problems
Subject: Indention Problems
When I indent, the preceeding task's duration changes to the same
duration
as
the current task. Also, when when unindenting or unoutdenting, how do you
remove or change the designation of summary or sub-task.