I have a project where all tasks have an envelope and an exclamation
point in the indicator column, and when you mouse over the indicator
it says "information for this task has changed please select Publish
New and Changed". But when I publish, it tells me that there is no
changed information. Even if I select All Information when
publishing, the indicator icons stay there. Any suggestions on why
the indicator icon in MSP 2003 do not disappear after publishing?
Thanks,
Kathy