Hi,

I'm creating a view in the MSP Web Access. Is there a way to add the
"Indicators" colum to the view? I'm looking a the Manage Views interface on
web access. It has all of the fields that are in my project except the
Indicators field. I believe this is a standard field in MS Project (not one
we created).

Thanks,
Paul
 
M

Marc Soester

Hi Paul,

I assume that you have created a new Project View ( not a Project Center
View). Please note that the indicator automatically appears for each Project
view. You dont need to choose the indicator when creating a view.

The same applies to the Project Center, only the indicator displays
different information to the Project task indicators ( e.g. Risks, Issue,
documents)

I hope that answeres your question
 
G

Gary L. Chefetz [MVP]

Paul:

Sorry, no. But you can detect certain values and represent them in custom
fields using indicators in PWA.
 