Indicators field in project web access.

L

Lee Newson

Hi,

when we use project web access with sharepoint and look at the project
center, the indicators field works just like it does in project and displays
any information for the relevant project, however when we look at an
individual project nothing appears in the indicator field, such as task
notes that we know are there when the schedule is open in project. Has
anyone else come across this problem, or does anyone know how i can make
task notes etc appear in the indicators field in project web access.

Cheers for any help in advance

regards

Lee
 
D

Dale Howard [MVP]

Lee --

Your first assumption is incorrect. The Indicators field in both the
Project Center and Project views in PWA does not work like the Indicators
field in the Microsoft Project plan. The Indicators field in PWA is used to
show Risks, Issues, and Documents in SharePoint. Hope this helps.
 
L

Lee Newson

Cheers Dale that makes more sense now.


Dale Howard said:
Lee --

Your first assumption is incorrect. The Indicators field in both the
Project Center and Project views in PWA does not work like the Indicators
field in the Microsoft Project plan. The Indicators field in PWA is used to
show Risks, Issues, and Documents in SharePoint. Hope this helps.
 