Shari K
I'm using Project 2000 with XP operating system. I want
to have one project that has 5 summary tasks that are
priority 1 - 5 and then have individuals assigned to the
subtasks as resources. But, in the same project I want to
have summary tasks 6 - 60 that have a mix of priorities
that can change month to month and have consolidated
resources assigned to the. Example, Summary tasks 1 - 5
will have John, Joe, Jim assigned individually to work
those tasks and then in summary tasks 6 - 60 I will have
18 engineers available for the work, but John, Joe, and
Jim may be part of those 18. I'm trying to find out who
is overallocated or underallocated plus determine if I
get some extra resources how much sooner will a task be
completed. Is it possible to mix individual and
consolidated resources in this way? thanks so much for
any suggestions.
to have one project that has 5 summary tasks that are
priority 1 - 5 and then have individuals assigned to the
subtasks as resources. But, in the same project I want to
have summary tasks 6 - 60 that have a mix of priorities
that can change month to month and have consolidated
resources assigned to the. Example, Summary tasks 1 - 5
will have John, Joe, Jim assigned individually to work
those tasks and then in summary tasks 6 - 60 I will have
18 engineers available for the work, but John, Joe, and
Jim may be part of those 18. I'm trying to find out who
is overallocated or underallocated plus determine if I
get some extra resources how much sooner will a task be
completed. Is it possible to mix individual and
consolidated resources in this way? thanks so much for
any suggestions.