J
JimS
Hi,
I'm trying to understand how MSP handles the work (remaining and actual) on
tasks, as I'm confused by how my plan is spreading the effort. We use flat
loading by default and don't directly change anything in the task usage view.
But we're sometimes seeing a tendency to load towards the front of the task
therefore skewing the planned progress.
I know that this doesn't give enough for an answer, but are there any links
to the logic that MSP uses?
JimS
I'm trying to understand how MSP handles the work (remaining and actual) on
tasks, as I'm confused by how my plan is spreading the effort. We use flat
loading by default and don't directly change anything in the task usage view.
But we're sometimes seeing a tendency to load towards the front of the task
therefore skewing the planned progress.
I know that this doesn't give enough for an answer, but are there any links
to the logic that MSP uses?
JimS