When you have several plans in EPM and you create a master plan linked
to them.

Within the greyed "Link Line" in the Master Plan only certain detail
fields have been copied accross information like Start and Finish, all
other info put into collums in the lower plans like people names and
comments are not copied up into the Master Plan.

Has anyone found a way round this problem without copying the
information from the lower level plans line by line to the master
plan. As when details change in the lower plans the master plan will
nott automatically update and you have to copy the information up
again.

Thanks in Advance
 
D

Dale Howard [MVP]

Martin --

In a Microsoft Project plan, external tasks only show a limited amount of
information in a project, as you have already discovered. I know no way
around this limitation. Hope this helps.
 