Insert Project into the Master Schedule

E

Eliane

Hi
I want to insert a project into a Master Schedule. So If
I insert a project, the project file name appears as 1
level and the project title as subtask (2 level) but the
project title was before I inserted it into the Master
Schedule a 1 Level task. So all Subtasks moved a level.
But I actually want to keep the old task levels so that I
see the actual Project title on the Master Schedule. I
know it should be possible. Nevertheless I don't know how
to do it. Please let me know if you can help.
Thanks
Eliane
 
G

Gérard Ducouret

Hello Eliane,

In the sub-projects, have you tried :
Tools / Options / View / clear the Show project summary task (at the right
bottom of the dialog)

Hope this helps,

Gérard Ducouret
 
B

BJ

Collapse the tasks above the point where you want to insert the project. The
project will then get inserted at the same level.
 
E

Eliane

Thanks that helps
-----Original Message-----
Hello Eliane,

In the sub-projects, have you tried :
Tools / Options / View / clear the Show project summary task (at the right
bottom of the dialog)

Hope this helps,

Gérard Ducouret

"Eliane" <[email protected]> a écrit dans le message de



.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top