"Insert Tasks from Timesheet" missing in PS07 Status Reports?

L

Langhorne

Our PS07 setup (set up pretty much using all the defaults right out of the
box) does not include the "Insert Tasks from Timesheet" button when creating
a status report that we we found to be very useful in PS03. Has this
functionality been removed? Or is it a configuration option I haven't found?

Thanks...

- Langhorne
 
D

Dale Howard [MVP]

Langhorne --

Yup, it's gone. There's no way to insert tasks in Status Reports in Project
Server 2007. Hope this helps.
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top