inserted project hours out of sync

A

abc123

Hello, I have about 10 projects that are each managed by seperate PMs. When I
insert these into a master project (they are not linked), the hours in the
master project do not reflect the hours in the subprojects. This is only
happening in the timephased portion of hours. I would like the master project
to reflect the subprojects exactly.

Thanks for your help
 