A
abc123
I work with several project files that are all managed by different PMs. I
would like to consolidate these into one master file for reporting, etc. To
do this, I select all of the projects that I would like to insert, uncheck
the link box, and click insert. This then inserts the subprojects into the
master. I end up with the following problem.
The hours on the right hand portion of the screen (the timephased portion)
are not the same in the master as they are in the original files. This is
only happening with 3 out of the 17 projects that are being inserted. The
other 14 project's hours are exactly the same between master and subproject.
I do not want the hours in the three projects to change at all. I want the
master project to reflect all of the original subproject files exactly.
I really appreciate your help, as I have been banging my head against the
wall for quite some time now trying to figure this one out.
would like to consolidate these into one master file for reporting, etc. To
do this, I select all of the projects that I would like to insert, uncheck
the link box, and click insert. This then inserts the subprojects into the
master. I end up with the following problem.
The hours on the right hand portion of the screen (the timephased portion)
are not the same in the master as they are in the original files. This is
only happening with 3 out of the 17 projects that are being inserted. The
other 14 project's hours are exactly the same between master and subproject.
I do not want the hours in the three projects to change at all. I want the
master project to reflect all of the original subproject files exactly.
I really appreciate your help, as I have been banging my head against the
wall for quite some time now trying to figure this one out.