R
RC
Hello, I thought I had figured out my problem this past weekend with
other helpful posts I found on this forum. I hope that I can have a
little more guidance.
I have a macro that exports timescaled data to excel. It also needs to
work for schedules with inserted projects, schedules with external
tasks, or a master project (consisting of only subprojects). I found
an earlier very helpful post that covers the bases if the macro is run
on a Task view (using OutlineShowTasks expaninsertedprojects:=True).
However, as this macro needs to be distributed to others, I am hoping
there is a method that I can use that does not need a Task view. Is
this possible?
Thanks for any help,
RC
other helpful posts I found on this forum. I hope that I can have a
little more guidance.
I have a macro that exports timescaled data to excel. It also needs to
work for schedules with inserted projects, schedules with external
tasks, or a master project (consisting of only subprojects). I found
an earlier very helpful post that covers the bases if the macro is run
on a Task view (using OutlineShowTasks expaninsertedprojects:=True).
However, as this macro needs to be distributed to others, I am hoping
there is a method that I can use that does not need a Task view. Is
this possible?
Thanks for any help,
RC