E
Elle
I want to have an integrated programme schedule that uses the same resource
is this possible?
At the moment i'm inserted the project and they all have their seperate
resources, which is fine but the reason i was the schedule is to add a couple
of test environments as resources so i can see when they are being used and
for which project so i can easuly see if they are over allocated?
Any ideas of a better way i can do this?
Thank you
Elle
is this possible?
At the moment i'm inserted the project and they all have their seperate
resources, which is fine but the reason i was the schedule is to add a couple
of test environments as resources so i can see when they are being used and
for which project so i can easuly see if they are over allocated?
Any ideas of a better way i can do this?
Thank you
Elle