Michael McGillick
I'm using Project 2000 to track the current project I'm working on. I've
defined my list of tasks and have chained them together so that I'm not
assigned to work on more than one task at a time. I understand that if I
adjust the hours for a particular task, the project end date either pulls in
closer or extends out farther depending on adjustment in hours to the task.
However, I also have one task that has a specific start and end date. How do
I get the rest of the schedule to flow around my fixed task and still make
project understand that during any given scheduled time, I'm only working on
a single task.
To be clear, let's assume that I was able to complete my first three tasks
prior to the task with the fixed time frame. If, for some reason, I needed to
extend the first task by a day, all other chained tasks would move out by a
day. What I would like to see happen is that Project automatically
recalculates the schedule to let me know that I should work on task three
until I reach the fixed task date, I should move to the fixed date task, and
then I should go back to task three to complete the remaining 8 hours work.
I'm looking to get the rest of the schedule to adjust without adjusting the
fixed task.
Any help would be appreciated. Thanks.
defined my list of tasks and have chained them together so that I'm not
assigned to work on more than one task at a time. I understand that if I
adjust the hours for a particular task, the project end date either pulls in
closer or extends out farther depending on adjustment in hours to the task.
However, I also have one task that has a specific start and end date. How do
I get the rest of the schedule to flow around my fixed task and still make
project understand that during any given scheduled time, I'm only working on
a single task.
To be clear, let's assume that I was able to complete my first three tasks
prior to the task with the fixed time frame. If, for some reason, I needed to
extend the first task by a day, all other chained tasks would move out by a
day. What I would like to see happen is that Project automatically
recalculates the schedule to let me know that I should work on task three
until I reach the fixed task date, I should move to the fixed date task, and
then I should go back to task three to complete the remaining 8 hours work.
I'm looking to get the rest of the schedule to adjust without adjusting the
fixed task.
Any help would be appreciated. Thanks.