B
Belinda Lee
In Project 2007, I cannot find how to insert a portion of a subproject
into a master project. I have 25 different subprojects that are all
organized by phases (Phase 1-5). The master needs to consolidate the
subprojects by these respective phases. For example:
MASTER
- Phase 1
--- From subproject 1
--- From subproject 2
--- From subproject 3
- Phase 2
--- From subproject 2
--- From subproject 3
--- From subproject 4
- Phase 3
--- From subproject 3
--- From subproject 4
--- From subproject 5
.... and so on and so forth. Can anyone help me?
into a master project. I have 25 different subprojects that are all
organized by phases (Phase 1-5). The master needs to consolidate the
subprojects by these respective phases. For example:
MASTER
- Phase 1
--- From subproject 1
--- From subproject 2
--- From subproject 3
- Phase 2
--- From subproject 2
--- From subproject 3
--- From subproject 4
- Phase 3
--- From subproject 3
--- From subproject 4
--- From subproject 5
.... and so on and so forth. Can anyone help me?