I need to be able to insert a task multiple times in a
plan. Example
Sub-Project 1
Task 1 Subproject 1 (a)
Task 2 Subproject 1 (b)
Release 1
Task 1 Subproject 1 (a)
Release 2
Task 1 Subproject 2 (b)
There are really only two tasks: a & b, they just show up
under different deliverables. Hyperlinks don't work for
this: they don't carry along with them the duration,
etc. I don't want to put the task in 2 times: that will
screw up the resource stuff.
plan. Example
Sub-Project 1
Task 1 Subproject 1 (a)
Task 2 Subproject 1 (b)
Release 1
Task 1 Subproject 1 (a)
Release 2
Task 1 Subproject 2 (b)
There are really only two tasks: a & b, they just show up
under different deliverables. Hyperlinks don't work for
this: they don't carry along with them the duration,
etc. I don't want to put the task in 2 times: that will
screw up the resource stuff.