Inserting new tasks causes project to auto add actual hrs?

L

Lil

I took over a project that needed task inserted. Also tracking actual hrs
worked per tasks. After I inserted the tasks, project started adding 8 hrs
per resource for actual hrs worked that I'm not entering. Why is this?
There are no impact to the actual hrs from the weeks prior to my changes
(working with Project 2003)--
Thanks
Lil
 
R

Rod Gill

Hi,

Can you tell us exactly what you did to get this result? Clearly it doesn't
seem right.

What version of Project, are you using Project Server, do you have an
automated time sheet system?

--
For VBA posts, please use the public.project.developer group.
For any version of Project use public.project
For any version of Project Server use public. project.server

Rod Gill
Project MVP
For Microsoft Project companion projects, best practices and Project VBA
development services
visit www.projectlearning.com/
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top