A
aho200
I am creating a subproject and have inserted this into a master project. The
master project is going to be very large for an $80 million dollar
implementation. I have tested inserting a subproject into a master and
seeing how dependencies can work in the master between subprojects. It seems
to work well. However, another senior project manager has said that the use
of subprojects in a master does not work well in MS Project and is not
recommended generally. Is this true? Are there any problems inserting
subprojects into a master as far as identifying the critical path, leveling
resources, etc.
Also currently both the master and subprojects are local projects.
When I import each of these into project server will I need to reinsert the
subproject into the master? Thanks
master project is going to be very large for an $80 million dollar
implementation. I have tested inserting a subproject into a master and
seeing how dependencies can work in the master between subprojects. It seems
to work well. However, another senior project manager has said that the use
of subprojects in a master does not work well in MS Project and is not
recommended generally. Is this true? Are there any problems inserting
subprojects into a master as far as identifying the critical path, leveling
resources, etc.
Also currently both the master and subprojects are local projects.
When I import each of these into project server will I need to reinsert the
subproject into the master? Thanks