We use External links in our Integrated Master Schedule. We build external
links from the Integrated Master Schedule to the sub-plans. The external
links in our Integrated Master Schedule are supposed to carry over all of the
values from the sub-plans. For some reason, the Baseline Start and Baseline
Finish do not carry over to the Integrated Master Schedule (external gray
links) all of the time. Instead of the Baseline Start and Baseline Finish
values carrying over into the Integrated Master Schedule, 'N/A' appears. Any
thoughts of why this is happening?
Thanks!
links from the Integrated Master Schedule to the sub-plans. The external
links in our Integrated Master Schedule are supposed to carry over all of the
values from the sub-plans. For some reason, the Baseline Start and Baseline
Finish do not carry over to the Integrated Master Schedule (external gray
links) all of the time. Instead of the Baseline Start and Baseline Finish
values carrying over into the Integrated Master Schedule, 'N/A' appears. Any
thoughts of why this is happening?
Thanks!