?Integration HRIS with Project Server 2007

S

Sanjay

Dear All,

I would like to seek your help on one issue. My company has got HRIS in
place and I need to integrate the Project server with HRIS resources list.
Please advise me if it is possible with Project server and if it is possible
what would be the procedure.

I eagerly look forward to your response.

Thanks & regards
Sanjay
 
R

Ray McCoppin

I have done this for other clients, using SAP and other ERP systems. This
is done like the Active Directory interface that is buildt in to Project
Server 2007. To sync the resources with external systems like HRIS. I see
two possiblities if HRIS has a interface to Active Driectory you might be
able to use the out box AD functionality to keep both systems in sync. Other
wise you will need to build a custom interface that sync's these two systems
using the PSI.
Here is a link to the active directroy sync code in codeplex.
http://www.codeplex.com/PS2007ADResSync

Hope this helps....
 
S

Sanjay

Thanks Ray for taking the time to reply. I will try below mentioned
possiblities, hopeing to succeed
 