Integration of project server 2007 and moss 2007 on separate serve

S

Sam

I have two server in one i have installed single server installation of
project server 2007 in which and on the other server separately i installed
moss 2007 and make Database server of MOSS 2007 is Project Server 2007.

Now we can integrate Project Server 2007 and MOSS 2007 in this way and want
to configure proposal workflow.

Because i dont want to install moss 2007 in existing installation of project
server 2007.
 
G

Gary L. Chefetz

Sam:

If you want to combine MOSS with Project Server, you need to make the two
servers part of the same farm and both need to have the same software
installed. You can always use hyperlinks to connect between the two farms.
Further, you do not need MOSS to use the Proposal workflow, so if that is
your only objective, you simply need to learn how to use built in workflow.
 