I've read through a lot of strings and tried the suggestions (custom field,
etc), but have had no success getting a finish variance from current to
interim plan. Also tried using Baseline1, but the formula 'Finish-Baseline1
Finish' does not calculate the deltas. Only the Baseline Finish variance is
accurate. I need an easy way to see variances from one update to another.
Please help!
etc), but have had no success getting a finish variance from current to
interim plan. Also tried using Baseline1, but the formula 'Finish-Baseline1
Finish' does not calculate the deltas. Only the Baseline Finish variance is
accurate. I need an easy way to see variances from one update to another.
Please help!