Hello,
I have a trouble with Users in Project Server 2003, wich I modify from MS
Project Professional 2003, Project Server synchronizes the Active Directory
User fromthe group, but when a user is deleted from AD, this user continue in
Project Server as a resource, even after the synchronization, and when I open
all resources from Resource Pool with MS Project Professional and try to save
changes, I receive an error messages. "Invalid User Account" although the
user no longer exist in AD.
Thanks for your time.
regards,
Carlos Vila
I have a trouble with Users in Project Server 2003, wich I modify from MS
Project Professional 2003, Project Server synchronizes the Active Directory
User fromthe group, but when a user is deleted from AD, this user continue in
Project Server as a resource, even after the synchronization, and when I open
all resources from Resource Pool with MS Project Professional and try to save
changes, I receive an error messages. "Invalid User Account" although the
user no longer exist in AD.
Thanks for your time.
regards,
Carlos Vila