T
thomasbcrowley
I am working in the Project Server2003 Enterprise environment. There seems
to be pro's and con's for having project managers use either line 0 or line 1
as the top level roll up line of their project. For example, if a user is to
open multiple plans in a single window, they will not see the line 0 baseline
inforamtion of the indivual projects. On the other hand, using line 1
needlessly uses an indenture level and posses the risk of additional lines at
the 1st level that do not roll up to the first line at the level1. What is
the suggested "best practice" regarding this dilima?
to be pro's and con's for having project managers use either line 0 or line 1
as the top level roll up line of their project. For example, if a user is to
open multiple plans in a single window, they will not see the line 0 baseline
inforamtion of the indivual projects. On the other hand, using line 1
needlessly uses an indenture level and posses the risk of additional lines at
the 1st level that do not roll up to the first line at the level1. What is
the suggested "best practice" regarding this dilima?