A
Andy S
I am using Project Pro 2007. I have an in-progress task that I am
capturing SV. The task was originally 20 days duration; however, it
will now require 40 days. I have changed the duration field, but the
SV does not reflect the new duration. I realize I am supposed to
baseline the new duration for the SV to update, but I only have 11
baseline fields to work with. I believe this schedule will encounter
more than 11 delays.
What is the best way to handle this situation? Re-baseline every
time? Create new tasks to capture the additional work that will be
needed? Stop using EVM?
Thanks!
Andy
capturing SV. The task was originally 20 days duration; however, it
will now require 40 days. I have changed the duration field, but the
SV does not reflect the new duration. I realize I am supposed to
baseline the new duration for the SV to update, but I only have 11
baseline fields to work with. I believe this schedule will encounter
more than 11 delays.
What is the best way to handle this situation? Re-baseline every
time? Create new tasks to capture the additional work that will be
needed? Stop using EVM?
Thanks!
Andy