Is it possible to EDIT the MultiValue Enterprise Resource Outline Codes 20-29
from the PWA Resource Center? Single value Enterprise Resource Outline Codes
20-29 seems to be the only option one has. your response would be greatly
appreciated.

Thanks in advance,
Spiro.
 
D

Dale Howard [MVP]

SpiroT --

When you select a resource in the Resource Center page and then click the
Edit Details button, the system displays only the single value entry version
of custom enterprise Resource outline codes 20-29. If you need to specify
multiple entries in an MV field, you must use Project Professional 2003 and
open the Enterprise Resource Pool. Hope this helps.
 
S

SpiroT

Thanks Dale.


Dale Howard said:
SpiroT --

When you select a resource in the Resource Center page and then click the
Edit Details button, the system displays only the single value entry version
of custom enterprise Resource outline codes 20-29. If you need to specify
multiple entries in an MV field, you must use Project Professional 2003 and
open the Enterprise Resource Pool. Hope this helps.
 