Is it possible to see in PWA the base calendar a project is using?

B

bobmcl

Is there a way to see what calendar a project is using in a Project Center
view? I would like to have a view that gives me a list of projects with a
field showing what base calendar the project is using.

The only method I have found for finding the project calendar setting is to
open the project in Pro, right click on the Gantt chart, and select the
non-working Time tab. Here it is displayed in the "Calendar" field - for
example "Standard (Project Calendar)", but I cannot find this field anywhere
in PWA or even Data Analysis.


Thanks,

Bob
 
J

Jan De Messemaeker

Hi Bob,

That isn't even sure. What the nonworking tab shows is the calendar serving
to format the gantt chart but that MAY not be the project calendar.

Project menu, Project Information is what you need.
Don't know about PWA though.

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 
B

bobmcl

Thanks Jan! I was not aware of the difference between the Gantt field and
the Project Information field.

Still looking for a way to get the field out of PWA if you come across that
information anywhere.

Thanks,

Bob
 