A
Ab_83
Hello,
The overall objective that I'm trying to achieve is to use Project t
schedule my team's work. We do allot of BAU Reporting, to which we hav
to stick to a rigid schedule, therefore I would like to be able t
assign a task that (for example) begins work day 1 and takes 5 hours.
Ideally i would like to then copy these taks into the following mont
(on which WD 1 could start on a different weekday).
I have set the Gantt Chart Timescales, so they show work days bu
cannot figure out if it's possible to set tasks using anything othe
than calendar dates.
I'm new to Project and I'm using 2000...any help would be greatl
appreciated!
Thanks
A
The overall objective that I'm trying to achieve is to use Project t
schedule my team's work. We do allot of BAU Reporting, to which we hav
to stick to a rigid schedule, therefore I would like to be able t
assign a task that (for example) begins work day 1 and takes 5 hours.
Ideally i would like to then copy these taks into the following mont
(on which WD 1 could start on a different weekday).
I have set the Gantt Chart Timescales, so they show work days bu
cannot figure out if it's possible to set tasks using anything othe
than calendar dates.
I'm new to Project and I'm using 2000...any help would be greatl
appreciated!
Thanks
A